APSC AE WRD 2019 PYQ: CPM Network

APSC AE WRD 2019 PYQ: CPM Network

CPM Network MCQ

CPM Network Multiple Choice Question

Question: CPM network is:
(A) Event oriented
(B) Activity oriented
(C) Slack oriented
(D) Float oriented
Answer: (B) Activity oriented

Explanation

The Critical Path Method (CPM) is a project management and scheduling technique used to plan and control large projects. In a CPM network, the focus is on activities, which are the tasks that consume time and resources. These activities are represented as arrows or nodes in the network diagram, while events mark the start or end of activities but are not the primary focus.

Key Notes

  • CPM is activity oriented, emphasizing tasks that require time and resources, such as construction or manufacturing processes.
  • In contrast, PERT (Program Evaluation and Review Technique) is event oriented, focusing on milestones or events rather than tasks.
  • Slack or float refers to the flexibility in scheduling non-critical activities but is not the primary focus of the CPM network.
  • CPM is widely used in civil engineering and project management to optimize schedules and resource allocation.

Note: The activity-oriented nature of CPM networks makes them essential for effective planning and execution of complex projects in civil engineering and other fields.

More solved questions of APSC WRD AE 2019, HERE

For APSC Water Resources Civil 2019 Question Paper, Click Here

For APSC Previous Year AE Question Paper, Click Here

For APSC Previous Year JE Question Paper, Click Here


Post a Comment

Previous Post Next Post